Second Concession North from North Sideroad to Beneteau Drive will be closed to through traffic from February 3 to October for the replacement of the bridge over the Long Marsh Drain.
Local residents will still be allowed to access their homes but delays should be expected, says the Town in a release.
“We thank you for your patience while we work to complete this capital improvement project,” said the Town.
“The Town reminds residents that during construction traffic disruptions may occur and some delays may be experienced. Please slow down and obey all traffic signage and watch for Flag Persons in the construction zone.”
The $1,182,600 project was awarded to Front Construction.